Example post
The Mill Street bridge is closing
By A. Reporter · 4 August 2026
Why it's closing
Inspectors found corrosion on two of the four support bearings during the routine survey in March, and rated the deck unsafe for vehicles over 7.5 tonnes.1 The council closed it to lorries that week and to all traffic a month later.
What the repair costs
The published figure is £2.4m, though the same document notes that a full deck replacement — likely within a decade — would cost roughly four times that.2
What happens to the 14 bus
It diverts via Cross Lane from the 12th, adding about nine minutes. The stop outside the library is suspended for the duration.